I have a job where I am not responsible for the design of the foundation system. I have all of my loads broken down into service dead, live, wind and seismic values. I prepare my reactions this way so that the foundation engineer can properly design his foundations.
The reactions have been submitted to the foundation engineer who is refusing to design the foundation until I give him worst case loading on his foundation system. Basically he is asking me to interpret the load combinations of the code for him. I avoid doing this because of the increased liability.
What do you guys do with providing reactions to another engineer to design foundations?
I understand with computer programs today, it is easy to export the reactions after they have been run through the load combinations.
The reactions have been submitted to the foundation engineer who is refusing to design the foundation until I give him worst case loading on his foundation system. Basically he is asking me to interpret the load combinations of the code for him. I avoid doing this because of the increased liability.
What do you guys do with providing reactions to another engineer to design foundations?
I understand with computer programs today, it is easy to export the reactions after they have been run through the load combinations.