Boiler106
Structural
- May 9, 2014
- 211
I need to design a post tensioned 12" podium slab to go as close as possible to the top-most elevated floor/roof of an existing building. This distance can be 6 inches to the underside of the deck or it could be 5 feet; we are trying to minimize it. The concrete column spacing is 32'x32'. There is a concern that conventional formwork would be too difficult to remove.
However, i am limited by two things: the new floor system cannot load the existing floor system, and any requirements for height and removal the shoring system might have.
We have considered foam, but are concerned that our loads will transmit through the surface to the floor below. Although, admittedly, i have not looked at the deformation compatibility b/w the two floor structures.
We have also considered a steel framed floor with metal deck that can be left in place.
Can anyone think of anything else?
However, i am limited by two things: the new floor system cannot load the existing floor system, and any requirements for height and removal the shoring system might have.
We have considered foam, but are concerned that our loads will transmit through the surface to the floor below. Although, admittedly, i have not looked at the deformation compatibility b/w the two floor structures.
We have also considered a steel framed floor with metal deck that can be left in place.
Can anyone think of anything else?