foxview11
Structural
- Sep 4, 2011
- 30
Our QC inspector requires us to remove the wet and loose soil which is present after excavation for footing to be supported by bored piles. As we can see in the site, the foundation level is below water table and it is not possible to compact the soil with required 95% compaction. Is it necessary to remove the soil and replace with granular fill for a footing resting on piles? I think, it may not be necessary since the footing is supported on piles.Please any expert on this, may I solicit your opinion. I am new on this kind of foundation..thanks a lot..