The fly ash did cause the problem since it raised the cost and was imposed late in the flow of things and the 2 month delay and weather compounded the situation.
A week or so earlier the same concrete and masonry contractor worked with the same G.C. to do the block walls (4' below grade and 20+' high) on a 100,000+ sf KMart over the Thanksgiving weekend (almost all on overtime), so there was always a constant communication there. Between 15 and 20 loads of block were delivered late Wednesday, steaks were on grill for lunch Thanksgiving Day and they were out of block on Friday morning and waiting for more. The remaining masonry was finished and braced Friday and Saturday in time for steel erection and roof beginning on Monday morning, so buried mechanicals were inplace for the slab to be poured later, obviously not with fly ash at that time of the year. Concrete finishing is very precarious in cool/cold weather and manpower has to be there and ready to start when the placed concrete is ready to be finished.
These jobs did not require the precision of a skating rink, but you have to let the concrete get ready before starting the finishing, which may require many people tied up (4 to 8 hours)waiting and scheduled. If the concrete contractor had done the smaller job, other projects would have been delayed.
The problem was the delays in the season and the last minute change to fly ash, to the small 30,000 sf slab caused construction problems and cost increases. Both the G.C. and the concrete/masonry supplier suffered problems at the wrong time of the year. The cost of the concrete was immaterial.
The problem was the last minute requirement for fly ash and unknown seasonally affected construction schedule.
If it is a small project, fly ash setting time is not a problem as long as there are good, reliable suppliers, since they have the mix designs and controls. Mass concrete (foundaions, dams, etc.) are definitely not a problem because they are not as critical and condition sensitive, but many ready-mix suppliers still carry a 10# bag of sugar in the truck for emergencies.
Dick
Dick
Engineer and international traveler interested in construction techniques, problems and proper design.