DakotaKid01
Structural
- Apr 23, 2015
- 3
I am designing a spread footing retaining wall to replace a pile supported retaining wall. The wall is adjacent to the abutment wall of road underpass for a railroad bridge. The road is being realigned so they are removing the pile supported wall and putting a spread footing one in the same general area. It was suggested to use 2' flowable fill under the spread footing to provide a more solid base than the soil because there are worries about settlement of the soil under the current pile supported base because it hasn't been loaded. Settlement would be bad because the wall needs to stay aligned with the abutment wall of the bridge because there is a sidewalk. The current design is barely passing sliding and bearing checks. Is a CDF under the footing a good idea? Are there any other suggestions? Is potential settlement an issue? Thanks.