We never follow the philosophy of "MAWP not to be limited by flange". In case some one wants to follow this philosophy, needs to review the entire system/ process before implimeting this philosophy. Some of the main reasons for not following this philosophy are as below;
1. Assuming that MAWP is limited by the flange rating which we do not want, we have following options;
a) Upgrade all the nozzle flanges to next higher rating. All the piping counter flanges, valves and instrument directly mounted on the equipment also require to have higher rating to connect with the nozzle flanges (rating of complete piping, flanges valves, instruments not upgraded). This will however not help in case of future de-bottlenecking as the complete system is not suitable for the higher rating.
b)Upgrade all the nozzle flanges along with the complete piping system (pipes, flanges, valves, instruments etc) to make it suitable for higher rating of the vessel. This may have a very big cost impact unless the piping circuit is a small circuit with low pressure rating and very few instruments, controls and valves. A big system even in low pressure rating (eg Nitrogen or Instrument air which is generally in 150# class and running all through the plant), if required to be upgraded to next higher rating just to meet vessel MAWP criteria, will have a big cost impact. Main process, high pressure systems with a lot of controls, instrumentation, valves will definetely have an extraordinary cost impact if we need to meet the criteria of "MAWP not to limit by flanges"
We also need to realize that most of the time piping class (pipe thickness)are based on flange rating pressure and not the process design pressure and change in flange rating will most likely require heavier pipe.
2. Above uprating and extra cost can not be justified for an unforseen future de-bottlenecking which may never happen also and if we are confident about future de-bottlenecking with increased pressure, why not select a higher design pressure from the day one?
3. Many times, I have personally seen that process design pressure is selected by based on the flange rating and not based on the actual operating pressure which may be much less compare to the design pressure. This is to allow any future de-bottlenecking upto the flange rating pressure without any change in the complete system (equipment, piping, valve, instruments etc). In such case, MAWP is mostly limited by flange and if I apply the criteria "MAWP not to be limited by flange", Its certainly overkill.