stoker123
Mechanical
- Mar 14, 2009
- 1
Steam cutting of a raised face 1500 lb 20 inch feedwater flange set has led to grinding the raised face 1/4" below B16.5 dimensions (raised face side). System design code is B31.1. System pressure is 1250 psig and temperature is 427 deg. F.
Schedule is pushing to not weld build back up. Machining will re-level face. Assuming no metal removal from the bolted faces (no degredation of strength structurally), is the risk only the potential to leak during operation with the reduced raised face? System flexibility will be checked for effect of 1/4 " make up. Is there any additional structural check that need be done?
Schedule is pushing to not weld build back up. Machining will re-level face. Assuming no metal removal from the bolted faces (no degredation of strength structurally), is the risk only the potential to leak during operation with the reduced raised face? System flexibility will be checked for effect of 1/4 " make up. Is there any additional structural check that need be done?