Good Day All,
I am designing multiple concrete structures which will house large lifting cranes, up to 20tonne lifting capacity.
I have searched far and wide but cannot find an example of a typical connection between the steel beam and the concrete corbel. I intend to bolt the bottom flange of the beam to the corbel (cast in bolts). Is it necessary to fix the top flange of the crane runway girder to the concrete column? If this is needed it may be problematic as we cannot cast bolts to the side of the column, so will have to post fix which is problematic as when drilling we could hit the rebar.
Has anyone done such a detail, how did you approach it.
Thanks!
I am designing multiple concrete structures which will house large lifting cranes, up to 20tonne lifting capacity.
I have searched far and wide but cannot find an example of a typical connection between the steel beam and the concrete corbel. I intend to bolt the bottom flange of the beam to the corbel (cast in bolts). Is it necessary to fix the top flange of the crane runway girder to the concrete column? If this is needed it may be problematic as we cannot cast bolts to the side of the column, so will have to post fix which is problematic as when drilling we could hit the rebar.
Has anyone done such a detail, how did you approach it.
Thanks!