Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Fire Pump Grouting

Status
Not open for further replies.

spkreng

Mechanical
Joined
Apr 7, 2010
Messages
55
Location
US
I have a fire pump and since the GC was going to pour more concrete, we set the pump up on 3/4" A. T. Rod with 1" sch 80 pipe nipples (sleeved the Rod) and they formed and poured the pump pad, my question is; the lower lip of the pump base is encased in the concrete so where does the NFPA 20 requirement come into play for grouting?

spkreng, CET
 
If I recalled correctly I had the same question while taking a NICET test.
The answer I found was that the entire based must be in contact with the concrete and the entire based must be filled with concrete as well. No empty pockets allowed.
 
I agree with NJ1. The last ten pumps I installed, the pad was formed all the way up to the bottom of the base plate which would fulfill your grouting requirement.

If we all agreed, we would be Communists.- Me.
 