kcall2
Geotechnical
- Nov 14, 2007
- 20
A site consists of a soft clay deposit about 10 to 30 feet BGS. The ground water elevation is about 8 feet BGS. Dewatering is not an option for environmental reasons and therefore adequate removals can not be performed. An areawide fill 20 feet in height is proposed. Static settlements are anticipated to be about 8 to 10 inches.
The obvious option is to build up the fill and let it sit until primary settlement is complete. Because of poor drainage, the time frame is unacceptable.
My question is: if an additional surcharge equal to about 10 feet of fill is added to the ultimate design height of 20 feet, can that additional 10 feet of fill be taken off before primary consolidation is complete, but after the anticipated settlement for ultimate conditions is exceeded?
Thanks for all the help.
The obvious option is to build up the fill and let it sit until primary settlement is complete. Because of poor drainage, the time frame is unacceptable.
My question is: if an additional surcharge equal to about 10 feet of fill is added to the ultimate design height of 20 feet, can that additional 10 feet of fill be taken off before primary consolidation is complete, but after the anticipated settlement for ultimate conditions is exceeded?
Thanks for all the help.