jdblake
Structural
- Feb 27, 2009
- 13
My project needs a 6' Tall chain-link fence installed onto an existing concrete barrier. The chain-link fence has slats in it making it a solid wall as far as wind is concerned. My wind pressure is 15 PSF.
The problem I'm having is how to attach the posts to the barrier. The top of the barrier is only 8" wide and ACI App. D really kills me with anchor bolts spacing. I'm looking into core drilling the barrier then grouting the posts in but don't know how to check for the correct embedment depth or concrete breakout. Is App. D applicable for concrete breakout? Is there another way to check for minimum embedment depth?
The problem I'm having is how to attach the posts to the barrier. The top of the barrier is only 8" wide and ACI App. D really kills me with anchor bolts spacing. I'm looking into core drilling the barrier then grouting the posts in but don't know how to check for the correct embedment depth or concrete breakout. Is App. D applicable for concrete breakout? Is there another way to check for minimum embedment depth?