I have a client who has asked us to write a procedure for "dry" pulling casings with a crane (i.e. no extraction hammer will be used)
His client and the crane manufacturer have their doubts, but I believe it's possible to proceduralize the process and perform the maneuver safely.
Do anyone have any experience of this process or developed any way to quantify the force needed to pull the casing?
The casing is 84" diameter and 60'-0" long.