KxKy
Geotechnical
- Mar 24, 2020
- 2
We are looking at options for a large stockpile embankment on a large property. However, there is an existing pipeline that is located outside of the property line running parallel to the slope face. We have noted that settlements beyond the property line are to be expected and that the pipeline will need to be monitored over the course of construction. The total settlements are on the order of 200 mm to 400 mm and will be relatively uniform along the pipe alignment as the soil profile is pretty uniform.
We noted that the client have a back up plan in place with the pipeline owner if movements are not acceptable to them. However, the client is nervous and does not want to damage the pipe. What sort of contingency measures can be taken? Would exposing the pipe and developing temporary supports work? Considered relocating the pipeline, but I feel that would be extremely expensive as well. Anyone in the community have some insight as to a reasonable contingency measure to address future pipeline settlement?
We noted that the client have a back up plan in place with the pipeline owner if movements are not acceptable to them. However, the client is nervous and does not want to damage the pipe. What sort of contingency measures can be taken? Would exposing the pipe and developing temporary supports work? Considered relocating the pipeline, but I feel that would be extremely expensive as well. Anyone in the community have some insight as to a reasonable contingency measure to address future pipeline settlement?