sponcyv
Structural
- Sep 25, 2007
- 137
In concrete pours, is there any information out there that gives guidelines to acceptable amounts of bleed water? I am wondering if there are any guidelines that limit the amount of bleed water in large concrete pours requiring several lifts. If a contractor pours the first lift and a noticable amount of bleed water is present on top of the concrete, should the contractor try to vibrate this concrete to get a better mix? I have researched this, but can not find any information.