Section VIII Div 1 vessel is already in service. No impact testing done. No available metal left from the heats used to fab that vessel.
Now we want to rerate the vessel for a lower MDMT, which would (in new construction) require impact testing.
Is there any feasible way to make this happen within code? I.e. is there any way around UG-84(i)?
Now we want to rerate the vessel for a lower MDMT, which would (in new construction) require impact testing.
Is there any feasible way to make this happen within code? I.e. is there any way around UG-84(i)?