Sprinkler 2
Man are you old…lol I started in 1978.
Even back in 78 everything got communicated via a letter. And then the calls started asking questions about what we wanted. Often it was just NFPA but sometimes it was an internal document taken from FM, IRI, IRM etc. particularly if not covered by NFPA say handing garments, flammable liquids, etc. But even a reference to NFPA we still had crazy questions. My office came up with a list of sprinkler contractors we worked with often and had a good working relationship with ie great design department when asked for recommendations.
So the process was meet with the client/insured get an idea what they were planning to do. Develop a letter outlining what sprinkler design we wanted, pump electric or diesel, PIV and WPV, hydrant location, etc etc. All driven by how much value or in insurance terms how much could we loose including building, contents (everything inside stocks, machines, racks etc)and business interruption(BI). Most times the BI would drive the numbers. Building and contents could be $25 million but BI could be $100 million depending on what they made. Remember when we actually made stuff in the USA???
We would review the plans with a letter of our approval or not. Visit the site when the system was going in to see what they said was going in was put in. Back to the site to review after everything was installed, witness fire pump acceptance tests. Again everything was documented during the process.
ESFR systems were so much fun when they 1st came out. I remember going to a new 1 million sq. ft warehouse with a ESFR system going in. All the heads were too far from the ceiling for ESFR. Contractor said been installing sprinklers for 30 years this how it is done you crazy insurance guy! I pull NFPA 13 out and show him… what it says. I do not think he made $$ on the job after raising all the pipe in the building.
So yea we got just a few calls from contractors…..lol
Thanks for the trip down memory lane…..