EPCM Service Costs 1

Status
Not open for further replies.

StacyFling

Chemical
Apr 13, 2014
3
Kindly advise what percentage should I consider for Engineering, Procurement and Construction Management (EPCM) Services Cost of the Total Project Cost.

Also for Erection and Commissioning what % of the Total Project Cost should be considered

Regards,
Stacy.
 
Replies continue below

Recommended for you

StacyFling,

These answers, particularly Erection and Commissioning, can be highly sensitive to geographic location, industry sector, union versus non-union labor, etc. What region are you concerned with?

I am in upstream oil and gas EPCM in Alberta, Canada, so what has worked for me is:

I usuually go in with EPCM at 7% to 10% of TIC for green-field, and EPCM at 15% of TIC for brown-field projects.

If you assume erection and commissioning at 40% to 50% of TIC for non-union labor, you are probably close.
 