COEngineeer
Structural
- Sep 30, 2006
- 1,186
I'm going to embed a tube steel to act like a flag pole for house basement remediation. I already sized the member and I assume the bottom is fixed and top is free. Can someone help where to start so that my assumption of fixed bottom is met? How deep I need to embed it into concrete, reinforcement around the tube steel, etc. I will have about 15 kips-ft at the base and about 9 kips of shear. Thanks!