I am reviewing a shop drawing for sign foundation. The two steel pipes supporting the sign go 15'0 below ground level and 25' above. The contractor is asking about the means of holding the steel pipes straight while pouring the concrete around it at the foundation level.
He does not want to use two cranes to hold the steel pipes (a suggestion by a senior engineer at my firm) as that would increase the construction cost.
I am guessing I could design a splice but I am not so sure about my approach in doing so.