Earned value

Status
Not open for further replies.

pzesco

Mechanical
May 27, 2011
4
In the 'Actual Cost' I have to consider the value of the sub-orders issued, or the value of the sub-orders already invoiced only?
Thanks
 
Replies continue below

Recommended for you

That should be according to your own accounting rules.

TTFN
faq731-376
7ofakss
 
Most companies that I've worked for consider orders placed as actual liabilities, since the cost must be realized unless the order is cancelled.

TTFN
faq731-376
7ofakss
 
Sometimes your contract specifies what you can call actual cost or work-in-progress value.

Best to you,

Goober Dave