Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Duration and Start&Finish Date

Status
Not open for further replies.

passco

Computer
Oct 7, 2009
2
Hi (sorry for my english, I'm Italian)
All activities on Project have each one a fixed Duration and it's possibile to execute all the activities in a certain period, for example 1 month. The sum of duration of all activities can be max 1 month or less.
it doesn't matter when I execute an acitivity, the important thing is to execute all the activity within the month.
Is it possible to fix the Start & Finish date from 1 to 31 day for each activity and left duration fixed?
Do you know other way to plan these activity type?
Thanks in advance.
 
Replies continue below

Recommended for you

Isn't that what a milestone date is for?

TTFN

FAQ731-376
 
Hi, thanks a lot.
It isn't possible to unrelate Duration from Start and Finish date? Is it possible move the duration without change Start or Finish date?
Thanks.
 
You're confusing Duration and Work. Work is the allocated time required to complete the task. Duration can be anything you want it to be.

TTFN

FAQ731-376
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor