OCI
Civil/Environmental
- Mar 15, 2007
- 82
One of my current projects is a 16' x 44' mat slab on drilled piers supporting 3 12'dia. x 32' x 162k (full) fermentation tanks (beer!). I had a geotech bore and provide me with recommendations (600psf skin for piers, K=50pci for mat). In one of my geotechnical books I found a method for computing short and long term settlement for the 18" drilled piers. Would you model these piers as springs or fixed? I would think some sort of spring would be correct but one of my co-workers dissagrees. My FEA model for the slab is greatly affected by what I set as boundary conditions. Thanks. This forum offers a wealth of knowledge and I will contribute to the best of my ability.