bnard
Civil/Environmental
- Oct 20, 2003
- 21
An existing river 3m wide with recorded water elevation at 1.25m during dry season and 2.5 during rainy season was diverted to give way for the subdivision development. Backfilling was made but compaction requirements were not observed w/c is at every 6". Residential houses built on top of the former river line shows signs of slab and wall cracking.
Surveys were conducted and found out that settlement indeed occurs. Remedial measures were made like injecting grouts within the perimeter wall foundation. There are 10 houses constructed on top of the former river line and only 3 shows signs of significant cracks.
Will there be any other applicable measures aside from grouts? Your assistance is very much appreciated.
Surveys were conducted and found out that settlement indeed occurs. Remedial measures were made like injecting grouts within the perimeter wall foundation. There are 10 houses constructed on top of the former river line and only 3 shows signs of significant cracks.
Will there be any other applicable measures aside from grouts? Your assistance is very much appreciated.