MCSEng
Electrical
- Dec 5, 2008
- 12
We are currently in the concept stage of a design involving the deployment of Solar PV System in an existing Electrical Power Distribution System on a Campus and are inviting different views on certain issues. A Diesel Standby Electrical Power Generator is also existing.
Two options are being considered: (1) Connect Many Smaller Gird-Tie Inverters Locally to Various Sub-Distribution Panelboards which are closer to the Photovoltaic panels; (2) Connect Fewer Larger Capacity Inverters to the Main Switchboard, which require cables to be laid over longer distances.
Key advantages of Option 1 are that the PV supply is closer to the loads and cables would not have to be laid over long distances, back to the main switchboard and could be the more feasible option. However, disadvantage is that this would require upgrading more sub-distribution boards since the prospective short circuit current at these points could be significantly increased; these panelboards are potential solar PV supply points for the rest of the power system and could carry increased loads under steady state conditions. Isolating the power system for maintenance would also be more complicated. These are amongst other disadvantages.
For Option 2, the advantages include simplicity in technical design and operation. Disadvantages include: high cost of laying cable from distributed generation points; electrical losses in longer cable running back to the main switchboards from remote PV Panels or Inverters.
Has anyone analyzed such a scenario? What were the other factors that were considered? Are there any technical articles, publication, standards etc. that provide guideline for various power system network configuration for Solar PV distributed on large acreage commercial and industrial sites? How is the matter of the Standby Diesel Generator handled during a power outage by the utility company?
Sorry for the long post. I saw a similar question but the focus was more on high voltage distribution.
Two options are being considered: (1) Connect Many Smaller Gird-Tie Inverters Locally to Various Sub-Distribution Panelboards which are closer to the Photovoltaic panels; (2) Connect Fewer Larger Capacity Inverters to the Main Switchboard, which require cables to be laid over longer distances.
Key advantages of Option 1 are that the PV supply is closer to the loads and cables would not have to be laid over long distances, back to the main switchboard and could be the more feasible option. However, disadvantage is that this would require upgrading more sub-distribution boards since the prospective short circuit current at these points could be significantly increased; these panelboards are potential solar PV supply points for the rest of the power system and could carry increased loads under steady state conditions. Isolating the power system for maintenance would also be more complicated. These are amongst other disadvantages.
For Option 2, the advantages include simplicity in technical design and operation. Disadvantages include: high cost of laying cable from distributed generation points; electrical losses in longer cable running back to the main switchboards from remote PV Panels or Inverters.
Has anyone analyzed such a scenario? What were the other factors that were considered? Are there any technical articles, publication, standards etc. that provide guideline for various power system network configuration for Solar PV distributed on large acreage commercial and industrial sites? How is the matter of the Standby Diesel Generator handled during a power outage by the utility company?
Sorry for the long post. I saw a similar question but the focus was more on high voltage distribution.