Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Dissimilar weld between P9 (9Cr 1Mo) and SS 304

Status
Not open for further replies.

starflex

Materials
Oct 17, 2015
40
Fellow members,

I am in the process of writing a pWPS for a dissimilar joint (high temperature piping for a power plant).

Base Material 1: P9 (9Cr 1Mm - Ferritic Steel)
Base Material 2: SS 304 (Austenitic SS)
Consumable: specifically requested to be EPRI87 (48% Ni, 37 Iron if I remember correctly)

Joint has to be welded under Australian Standard (AS3992 for the qualification and 1210 as Pressure Equipment Standard, plus other to be applied for pre-heat, etc). AS far as I remember from my never-applied studies, I have to do the buttering first on the ferritic side, PWHT the ferritic and then I can perform the welding on the joint (without final PWHT because of the austenitic SS).

Pre-heat, interpass and PWHT temperatures for the buttering are not a problem. I can find them, not an issue.

My concern is, however, when I perform the joint. Should I pre-heat, perhaps from the ferritic side? Austenitic SS would recommend to avoid it, and I am not welding directly on the ferritic steel too (as I am welding on the buttering layers). Should I just avoid the pre-heat and keep a maximum interrun of 150 Celsius?

 
Replies continue below

Recommended for you

Your DMW should be performed as follows;

1. Deposit a butter layer over the 9Cr-1Mo side of the weld prep. Use a preheat of 400 deg F for this butter layer.
2. Subject the 9Cr-1Mo base material after buttering to PWHT.
3. Once this is completed, you join the buttered and PWHT 9Cr-1Mo end to the 304 ss using P87 filler metal with no preheat or PWHT.
 
Metengr,

That makes a lot of sense to me. Thank you for that.

Only concern (perhaps misinterpretation of your words, as I am not a native English speaker) is that one butter layer may not be enough; I was prone to think about two or three consecutive layers and then do the PWHT on the 9Cr-1Mo (TIG process, under the hypothesis of worst case scenario of 40% dilution).
 
The butter layer thickness is up to you because you are using the P87 filler metal developed by EPRI.
 
Are you using 304L or dual-certified 304? If yes,the preheat shouldn't be that deleterious! We did various tests up to about 300 C inter-pass temp for 304L piping and there is no carbide formation due to low carbon content. However, I am not familiar with AS3992 and 1210 requirements.

By the way, I totally agree that the safest way is to use butter passes.

 
Gents,

Thanks a lot for your help.

The material is actually Super 304H - in my understanding, it contains a certain amount of copper (3% ?) .

Does it change ?
Sorry, I should have it specified before.
 
Yes, in that case you need to use a Thermanite 617 (ENiCrCoMo-1) filler metal in lieu of EPRI87. The rest of the method remains the same.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor