port125
Civil/Environmental
- Jan 15, 2009
- 64
I am doing the connection design for several Directly welded flange FR Moment connections, when I break the resisted moment into the tension and compression components I find that the beams flanges are not adequate to handle the forces.
Does anyone know if we can use the beam web connection to resist the remaining moment? Also are there any good references that illustrate a similar problem?
A similar connection is solved out on the AISC 13 reference CD, however they never run a check on the beam flange.
Does anyone know if we can use the beam web connection to resist the remaining moment? Also are there any good references that illustrate a similar problem?
A similar connection is solved out on the AISC 13 reference CD, however they never run a check on the beam flange.