cinephile00
Civil/Environmental
- Dec 19, 2004
- 4
Hi, guys. I'm looking for an information on the on-going (still under construction) project with a diaphragm wall embedded into medium/hard rock more than 4m.
It does not matter where the project site is globally.
The design of my project requires the diaphragm wall to be inserted into med/hard rock more than 4m with a rock pin or H-pile down below.
The profile is; Top 15m is the sandy silt with gravel and below 15m is med/hard rock of 55~100MPa UCS values.
Total excavation depth is 30m, which gives average 19m D-wall and 11m toe pin below.
However, the local sub contractors do not have a proper equipment or experience for this 'deep' rock embedment scheme.
This is due to the fact that normal local geology here has 'sound' weathered rock above the base rock and usually less than 1m embedment into the base rock is enough for the D-wall stability.
This situation requires me to find a project of the same or similar condition.
If possible, I'm considering to visit the site and the contractors to see the actual construction with my subcontractors.
Thanks.
Paul
It does not matter where the project site is globally.
The design of my project requires the diaphragm wall to be inserted into med/hard rock more than 4m with a rock pin or H-pile down below.
The profile is; Top 15m is the sandy silt with gravel and below 15m is med/hard rock of 55~100MPa UCS values.
Total excavation depth is 30m, which gives average 19m D-wall and 11m toe pin below.
However, the local sub contractors do not have a proper equipment or experience for this 'deep' rock embedment scheme.
This is due to the fact that normal local geology here has 'sound' weathered rock above the base rock and usually less than 1m embedment into the base rock is enough for the D-wall stability.
This situation requires me to find a project of the same or similar condition.
If possible, I'm considering to visit the site and the contractors to see the actual construction with my subcontractors.
Thanks.
Paul