EngSD
Structural
- Dec 1, 2010
- 29
I have a question about diaphragm load transfer that I am hoping someone can help me with. I am working on a wood framed building that has a gable roof coming in perpendicular to another gable roof (see sketch). I don't have any lateral resisting system in the portion of the building that is below the perpendicular gable roof due to wall openings. I am wondering if it is possible to transfer the diaphragm forces through the valley of where the two roofs meet so that I can use the lateral force resisting system of that portion of the building. Was thinking something maybe like Simpson coil straps evenly spaced along the valley?