Robbiee
Structural
- Jan 10, 2008
- 285
Typically rebars are spliced in the pour strips in suspended slabs. If rebars are NOT spliced, i.e. continuous, and the concrete is poured after 28 days from pouring the adjacent panels, is that any helpful for releasing shrinkage stress?
Thanks for the input.
Thanks for the input.