Assuming you are following ASME standards...
1. If the detail view is not a section, it would not violate ASME Y14.3-2012 to take a section from the detail.
2. Nested detail views are sometimes necessary to get a clear understanding of what the drawing is defining, and do not violate ASME Y14.3-2012.
Bottom line is to make the drawing as easy to interpret, within the standards (company, ISO or ASME), as you reasonably can.
Some CAD packages come OOTB following the ASME standards but allow for changing the settings to do what would otherwise be considered bad practice, such as creating a section from a section. As long as these "bad" practices are documented, it is acceptable to follow them.
"Know the rules well, so you can break them effectively."
-Dalai Lama XIV