patigerjet
Civil/Environmental
- Apr 27, 2007
- 1
I'm working with a fairly large & complex 2.5 mile storm diversion pipe preliminary DESIGN project of twin 42" pipes with storm inlets placed every 300-400' along/above the twin interceptor. The twin interceptor is to be installed just above and parallel a very high stone quarry wall operation that may be failing from the high storm flows above the stone wall. The twin interceptors will first be largely fed above by a cheap but effective asphalt open-lined channel. The channel though has to be switched to an sub-grade pipe interceptor because of site limitations from building & equipment operations of the quarry.
What I need to determine is how to design an effective catch basin inlet system to feed the the sub-grade twin interceptor from above it. The key I assume will to largely sump the inlets with large volume grates since I am looking at large catchment areas (>300-500 acres total).
Any ideals guys on a effective/innovation inlet design approach along the interceptor. Am I also looking at combining the inlets by installing intercepting headwall culverts where I can track down locations where more heavily concentrated/channel flows are evident along the interceptor pipe and tieing these into the twin pipe interceptors.
Thanx
What I need to determine is how to design an effective catch basin inlet system to feed the the sub-grade twin interceptor from above it. The key I assume will to largely sump the inlets with large volume grates since I am looking at large catchment areas (>300-500 acres total).
Any ideals guys on a effective/innovation inlet design approach along the interceptor. Am I also looking at combining the inlets by installing intercepting headwall culverts where I can track down locations where more heavily concentrated/channel flows are evident along the interceptor pipe and tieing these into the twin pipe interceptors.
Thanx