pob11646
Structural
- Mar 8, 2009
- 35
I have got a general question about the design of a combined footing vs. a single footing. I have just finished a design of a single footing for a storage silo. It is founded on grade, with a soil bearing capacity of 3 ksf. My footing will be a 19 ft by 19 ft by 3 ft thick footing, reinforced top and bottom by #6 at 12" O.C. top & bottom each way. I analyzed for overturning moment, sliding for gravity loads, wind and seismic forces.
Now, I have to enlarge my footing to take into consideration the construction of a similar footing for similar loads just adjacent to my current footing.
I would not be constructing the whole combined footing all at once, because the while the first storage silo is for present use, the second one is for future. In effect, I would only be constructing, say 1-1/3, or even 1-1/4 of the combined footing for now.
Would designing a combined footing for two of these storage silo structures be the best way to do it? I would design a combined footing for both of the structures, but only construct, say 1-1/3 of the combined footing, leaving the rest to be constructed when it is required. Is this the best approach? Intuitively, I would think that my previous design would also work, but I just need to double the size of the footing. Would this be correct?
In fact, I would also intuitively think, without starting my design, that doubling my previous design would be conservative, and that my combined footing could actually be smaller in footprint and thickness? Would this also be accurate?
What would be the best way to approach the design of a combined footing?
What is the best way to allow for the construction of the rest of the footing? Mild steel dowels embedded in the first footing, and greased on the exposed end? Any other suggestions? Thanks.
Now, I have to enlarge my footing to take into consideration the construction of a similar footing for similar loads just adjacent to my current footing.
I would not be constructing the whole combined footing all at once, because the while the first storage silo is for present use, the second one is for future. In effect, I would only be constructing, say 1-1/3, or even 1-1/4 of the combined footing for now.
Would designing a combined footing for two of these storage silo structures be the best way to do it? I would design a combined footing for both of the structures, but only construct, say 1-1/3 of the combined footing, leaving the rest to be constructed when it is required. Is this the best approach? Intuitively, I would think that my previous design would also work, but I just need to double the size of the footing. Would this be correct?
In fact, I would also intuitively think, without starting my design, that doubling my previous design would be conservative, and that my combined footing could actually be smaller in footprint and thickness? Would this also be accurate?
What would be the best way to approach the design of a combined footing?
What is the best way to allow for the construction of the rest of the footing? Mild steel dowels embedded in the first footing, and greased on the exposed end? Any other suggestions? Thanks.