Floor loads - will be furnished by equipment vendors through requests from the owner. A ball park easimate on the uniform floor live load is about 150 psf, similar to that for telecommunication centers.
The remaining items would require inputs from the equipment vendors, and project electrical engineers. Also, archetects, and HVAC engineers play very important roles as well. Structural group generally has the least say on these matters.
I would anticapate interior raised floors, equipment racks, and cable trays. Keep in mind that the final equipment weight could very well exceeds that listed on the initial submittal, and revisions on interior arrangement are a frequent phenonmenon, so, be conservative (on assumptions)and generous (on material sizes) in preliminary design, and always anticipate changes.