ajk1
Structural
- Apr 22, 2011
- 1,791
Does anyone have an expression, or a procedure, or a spreadsheet for determining the depth of drilled concrete pier to use to take the force and moment from a bollard post that extends down into the drilled pier, when there is asphalt paving at the surface that can resist horizontal force? I am trying to resist about 3000 pound horizontal load applied at 20" above the asphalt.