There's a method of payment that says 50% of the price at placing order, 25% upon delivery and another 25% one month later. Now I can only make a resource curve that will describe how the resource is used throughout its duration. for example if it were 50% and 50% i would make the resource curve sth like this: (50 0 0 0 0 0 0 0 0 50).
But because of the 25% that extend after the duration of the activity i can't input the right distribution.
Is there any other way besides adding a new activity and a new resource?

Thank you
 