In the drawing, a schedule for deflection is provided, which requires a 1 1/2" deflection where beams are located 30' or less. I asked the architect for the project if this was to be 3/4" up and 3/4" down. He stated the EOR said it was provided for down only. Is that typical to have 1 1/2" deflection for down only? It seems to me that a building could deflect up or down.