I came across this document published by CEATI international, Distribution Overcurrent Protection.
I went through the whole 240 page document and found some interesting information about coordination between fuses, reclosers and station breakers. One of interesting arguments was to have a time delay element instantenous overcurrent element with .067 secs delay.
What I want to know is the impact of a time delayed 50 element on the equipment damage curve. It cannot be visually imagined. Could you please shed some light on this concept?
Thanks
I came across this document published by CEATI international, Distribution Overcurrent Protection.
I went through the whole 240 page document and found some interesting information about coordination between fuses, reclosers and station breakers. One of interesting arguments was to have a time delay element instantenous overcurrent element with .067 secs delay.
What I want to know is the impact of a time delayed 50 element on the equipment damage curve. It cannot be visually imagined. Could you please shed some light on this concept?
Thanks