Hi Everybody,
The facility I am at (large convention center) has dozens of 480 volt 125 kva 3 phase power transformers to supply power to exhibitors. Even with no shows the unloaded transformers are energized costing about $800/ day in energy costs. The heat then must be removed by HVAC costing even more.
I would like to cycle these off when there is no event. This would mean turning the unloaded transformers off/on via a breaker about three times a week. In some cases certain transformers may be off for months.
The transformers are in clean air-conditioned tunnels and humidity can be controlled.
Am I going to save money with this scheme or is pre-mature equipment failure of the transformers and breakers going to out weigh power savings?
Thanks,
Andy
The facility I am at (large convention center) has dozens of 480 volt 125 kva 3 phase power transformers to supply power to exhibitors. Even with no shows the unloaded transformers are energized costing about $800/ day in energy costs. The heat then must be removed by HVAC costing even more.
I would like to cycle these off when there is no event. This would mean turning the unloaded transformers off/on via a breaker about three times a week. In some cases certain transformers may be off for months.
The transformers are in clean air-conditioned tunnels and humidity can be controlled.
Am I going to save money with this scheme or is pre-mature equipment failure of the transformers and breakers going to out weigh power savings?
Thanks,
Andy