Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Customize timescale for gantt chart?

Status
Not open for further replies.

mscatcard

Computer
Mar 17, 2005
2
I need to use a custom timescale for my MS Project schedule - instead of months and weeks I need Period 1 Week 1, Period 1 Week 2, etc. Is there some way to modify the timescale at the top of the gantt chart view to do this? Or is there an easy way to export a gantt chart to Excel so I can do my own timescale?
 
Replies continue below

Recommended for you

Im looking for the same customization. Are you somehow related to Mars? If so, i would like to get in touch.
If you find a solution for this, could you post it pls?.
 
Go to the Main Menu / Format/ Timescale. For each tier: top, middle, bottom select the units: years, months, weeks etc and select the LABEL. The label can either be a calendar date of a generic year1, months 1, week 1.

Try it!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor