Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations 3DDave on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Curing of Masonry Walls Question

Status
Not open for further replies.

Berniedog

Structural
Dec 19, 2005
200
I designed a 18'-0" high, 12" masonry wall. The inside is protected from the elements and the outside is not (Michigan -45 degrees +-). How long should it cure before placing roof joists on them?
 
Replies continue below

Recommended for you

Depends on the load and the strength of the grout. Masonry code requires 2000 psi grout but in the Cincinnati area I find we usually get 3000 psi grout. I would check the capacity with full dead and 3/4 of the live and wind (normal load combinations) to determine what would be required. I would not expect to need more than 3 to 7 days if you are getting 3000 psi grout. Chances are with 12" CMU the face shell will handle the gravity loads. Just be wary of the wind, which may still work as a 12" unreinforced gravity wall anyway if it is reinforced as an intermediate reinforced shear wall.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor