canwesteng
Structural
Is anyone aware of a way to weasel out of the maximum spiral pitch in CSA A23.3? Specifically regarding clause 7.6.4.3 (7.6.4.4 in 2004), giving the max clear of 3". Contractors often want to use spirals for piles (understandable as they hold their shape well), but usually just suggest swapping tie spacing with spiral pitch. I'm thinking there must be a way to weasel out of this, otherwise why are yards even set up to make spirals at an 8"/10"/12" pitch?