martin888888
Civil/Environmental
- Jun 15, 2010
- 157
We have a project where we are simply reshaping 2000' of creek. In the process we are going to be creating some cut material which we are going to be allowed to placed above the creek as long as positive flow is maintained to creek. Fill above creek bank will be 1' in depth and extended 7' from top of bank. Would you normally require the contractor to do compaction testing and submit results for something like this?