Boeing has, since 1958, certified the first 707, 720, 727, 737, 747, 757, 767 and 777. THE AVERAGE DAYS BETWEEN ROLL OUT AND FIRST FLIGHT HAS BEEN 61 DAYS — TO CERTIFICATION — 349 DAYS. The July 8 2007 (aka 7-8-7). was a dog & pony show that detracts from the skills of the many talented and dedicated people in the Boeing family. . . . the 777 required 370 days and someone thinks they can accomplish 787 flight & Certification testing in less than six months?
jim