klipper
Structural
- May 2, 2002
- 7
Hi all,
I have been getting a number of requests for new crane system foundations to be installed into existing facilities lately. The crane system vendors sell to customers by placing the new crane columns as close to exterior walls as possible (face of column just inches from wall face). It has been my practice in the past (maybe too conservatively) to locate the columns so I can install a new rectangular footing next to the existing wall's spread foundation and also to match the bottom of the existing wall foundation. Customers do not like to hear that I would like them to move the columns away from the wall after the have been sold a bill of goods from the crane contractor showing the columns right against the wall. I know I have seen other engineers design a foundation for a column tight to the wall where a new pier is installed and then a foundation is poured over the top and along side the wall's strip footing and the new foundation is doweled to the old. I suppose if the proposed new foundations were small enough, you could undermine the wall footing and pour the new foundation under the wall footing if you design the new for the wall load as well. I have also heard of people cutting the existing wall's strip footing flush with the wall to allow the installation of the new crane foundation. What are you guys doing as common practice and what are your theories on the best practice?
Thanks in advance.
I have been getting a number of requests for new crane system foundations to be installed into existing facilities lately. The crane system vendors sell to customers by placing the new crane columns as close to exterior walls as possible (face of column just inches from wall face). It has been my practice in the past (maybe too conservatively) to locate the columns so I can install a new rectangular footing next to the existing wall's spread foundation and also to match the bottom of the existing wall foundation. Customers do not like to hear that I would like them to move the columns away from the wall after the have been sold a bill of goods from the crane contractor showing the columns right against the wall. I know I have seen other engineers design a foundation for a column tight to the wall where a new pier is installed and then a foundation is poured over the top and along side the wall's strip footing and the new foundation is doweled to the old. I suppose if the proposed new foundations were small enough, you could undermine the wall footing and pour the new foundation under the wall footing if you design the new for the wall load as well. I have also heard of people cutting the existing wall's strip footing flush with the wall to allow the installation of the new crane foundation. What are you guys doing as common practice and what are your theories on the best practice?
Thanks in advance.