mscud
Structural
- Oct 15, 2012
- 1
This is my first post so I apologize if something is incorrectly set up.
I am a young engineer at a precast concrete company just finishing up my first project. Through out the job we had a number of locations where cracking occurred in the concrete around welded connections. This cracking was determined by the head engineer to be created by the heat caused during welding. On Thursday I have to go sit in on a close out meeting with the GC at which they are going to accuse us (the manufacture/designer) of causing these cracks.
I am looking for an unbiased opinion on who is typically at fault when it comes to these issues, the producer, the engineer, or the welder.
Some details:
- All of the connections are 100% stainless steel (304)
- Cracks have been observed on wall-to-wall, DT-to-DT (JVI vectors), and even anti-roll connections under beams.
From what I’ve read, it sounds like this is an issue with both welding and production. No clear space was provided between the plates and the concrete. So the plates did not have any room to expand. Also, the welders never allowed the plate to cool during welding on any connections.
Any information or links to publications on this topic would be greatly appreciated.
Thank you
I am a young engineer at a precast concrete company just finishing up my first project. Through out the job we had a number of locations where cracking occurred in the concrete around welded connections. This cracking was determined by the head engineer to be created by the heat caused during welding. On Thursday I have to go sit in on a close out meeting with the GC at which they are going to accuse us (the manufacture/designer) of causing these cracks.
I am looking for an unbiased opinion on who is typically at fault when it comes to these issues, the producer, the engineer, or the welder.
Some details:
- All of the connections are 100% stainless steel (304)
- Cracks have been observed on wall-to-wall, DT-to-DT (JVI vectors), and even anti-roll connections under beams.
From what I’ve read, it sounds like this is an issue with both welding and production. No clear space was provided between the plates and the concrete. So the plates did not have any room to expand. Also, the welders never allowed the plate to cool during welding on any connections.
Any information or links to publications on this topic would be greatly appreciated.
Thank you