Crack Control - 2005 LRFD Interims

Status
Not open for further replies.

BradPL

Structural
Joined
Jul 8, 2005
Messages
12
Location
US
Has anyone started working with the AASHTO 2005 LRFD Interim Revisions? Section 5.7.3.4 has changed in that the Z parameter is no longer used for crack control in concrete. There is now a gamma factor that controls the spacing of reinforcing.

I'm using a gamma factor of 1.00 for Class 1 Exposure Conditions which according to the code is suited for deck design. According to my calculations I'm getting a maximum reinforcing spacing in the neighborhood of 5 inches. Calculating using the old Z of 130 for extreme exposure worked fine for my reinfocing spacing of 8 inches.

Is anyone else getting much more restrictive spacings than the old method?

Thanks in advance.
 