Is there no way to edit my existing post?


I need to tie a support activity to a string of tasks such that it acts like a hammock - that is it's duration mimics that of the string of work activities. There is a fixed cost per hour associated with the support activity that I would like to be able to show.

Is this something I'm going to have to manage manually?

Primavera P3 3.1 sp2

Thanks for your help
 