I am currently trying to research the effects of adding additional ducts through a brick wall by coring. The existing wall in a chamber has 100mm diameter ducts 500mm spacing (centres) and I am looking into doubling up total number of ducts. Therefore spacing would be 250mm centres and brickwork between ducts would be 200mm. The loading on the chamber would be 5kN/m2
Can anyone point me in the right direction as to determine minimum duct/core spacing requirements in brick walls (UK).