Question: Where should construction joints be located in a two-way slab?
I am involved in the construction of an underground tank with a two-way concrete roof slab. The column spacing is about 22.5 and the tank is 270' x 90'. I have been asked by the contractor where he should locate the construction joints. There will be two construction joints for the slab. This will divide the slab into three seperate pours. Should the construction joints be located at the mid-span where the shear is almost zero - or - should the joints be located at the third points where the moments are almost zero.
I am involved in the construction of an underground tank with a two-way concrete roof slab. The column spacing is about 22.5 and the tank is 270' x 90'. I have been asked by the contractor where he should locate the construction joints. There will be two construction joints for the slab. This will divide the slab into three seperate pours. Should the construction joints be located at the mid-span where the shear is almost zero - or - should the joints be located at the third points where the moments are almost zero.