hanksmith
Electrical
- Feb 7, 2008
- 64
Currently working on the design of a concrete encased electrical conduit bank, have to install 600V feeds and about 1200A, currently looking at3/phase of 750kcmil.
My question comes with the conduit bank and how many bends I can have before it starts getting hard to pull the cables through, the run I have is only about 40m or 130ft. Right now I am thinking I will have a 90 at the start of the run and a 90 at the end, will the installing contractor be able to pull this cable?
Does anyone have any links to literature, I might need something to justify the need of a pull pit?
Thanks
Hank
My question comes with the conduit bank and how many bends I can have before it starts getting hard to pull the cables through, the run I have is only about 40m or 130ft. Right now I am thinking I will have a 90 at the start of the run and a 90 at the end, will the installing contractor be able to pull this cable?
Does anyone have any links to literature, I might need something to justify the need of a pull pit?
Thanks
Hank